After the Asphalt was removed, the soil underneath was excavated to allow for a minimum of 14 inches of natural, crushed limestone(21aa). Before installing the gravel, the sub base was properly compacted and a Geo-textile Membrane Fabric was installed. After the 21aa was installed and compacted in 3" lifts, a bedding course of 2-N-S natural sharp sand formed a perfectly sloped screed to install the pavers onto.
The front entry path was also replaced with pavers, the pattern continuously flows from the drive to the front door.
As a courtesy, we will return to re-sweep paver jointing sand into all joints before the end of this season. The surrounding grade and Landscape will also be properly modified at this time. This was an excellent early October project and the weather was perfect for the work we completed.